Microsoft 074-343 : Managing Projects with Microsoft Project 2013

  • Exam Code: 074-343
  • Exam Name: Managing Projects with Microsoft Project 2013
  • Updated: Sep 17, 2026
  • Q & A: 110 Questions and Answers

Already choose to buy: "PDF"

Total Price: $59.98  

About Microsoft 074-343 Exam Questions

Planning a certification path, not just one exam? Discuss a long-term discount with VCEDumps — the Microsoft Managing Projects with Microsoft Project 2013 set, with 110 practice questions for the 074-343 exam, is a good first step.

Microsoft 074-343 Exam Overview:

Certification Vendor:Microsoft
Exam Name:Managing Projects with Microsoft Project 2013
Exam Number:74-343
Related Certifications:Microsoft Certified Professional (Historical)
Available Languages:English
Real Exam Qty:40–60 (typical Microsoft exam length estimate)
Passing Score:700 / 1000 (scaled score)
Exam Format:Multiple choice
Sample Questions:Free Download real 074-343 actual tests
Pre Condition:Experience using Microsoft Project 2013 and core project management concepts recommended

Microsoft 074-343 Exam Syllabus Topics:

SectionObjectives
Topic 1: Initialize a Project- Set up calendars and custom fields
- Create a new project and templates
Topic 2: Manage Resources and Assignments- Manage resource allocations and assignments
- Enter and edit resource information
Topic 3: Communicate Project Information- Share data with other applications and SharePoint
- Customize views and reports
Topic 4: Create a Task-Based Schedule- Build logical schedule with dependencies
- Define project information and task structures
Topic 5: Track and Analyze a Project- Update and compare project progress
- Set and maintain baselines

Microsoft 074-343 Exam: Questions Candidates Ask

Experience using Microsoft Project 2013 and core project management concepts recommended Vendors revise eligibility rules periodically, so confirm the current requirements on the official page before registering.

Delivery is instant — an automatic email within a minute of payment, unlimited devices, and 7*24 online service (replies within two hours) if anything's missing after 2 hours; check spam first. If you fail the corresponding 074-343 exam within 60 days of purchase, we refund all the cost you paid: send a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam, processed within 7 days. Excluded: exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products. Alternatively, exchange for two equal-value products free.

The Microsoft Managing Projects with Microsoft Project 2013 blueprint spans 5 domains — including Manage Resources and Assignments, Create a Task-Based Schedule, Communicate Project Information. Study in proportion to the weightings; the complete outline above details every subtopic.

Yes — free demo downloads let you tell whether the Microsoft Managing Projects with Microsoft Project 2013 material suits you before purchasing. Purchases include 365 days of free updates, each new version emailed immediately; renew afterward at 50% off.

The Microsoft Managing Projects with Microsoft Project 2013 is Microsoft's certification exam for Microsoft Project, at the Specialist level. These certifications are valued precisely because they're demanding — passing one validates real capability. Related credentials include Microsoft Certified Professional (Historical).

Microsoft Managing Projects with Microsoft Project 2013 Sample Questions:

Question #1

You are a project manager for an organization that uses Project Standard 2013.
You add shortcuts on the Quick Access Toolbar to your most frequently used commands.
Your manager is impressed with the ease of use this customization provides and would like other project managers in the group to use it.
You need to deploy the customization to these project managers.
What should you do?

  • A. Email your global.mpt file to each project manager. Ask them to place the template in the %appdata%\Microsoft\MS Project\15 \1033 folder.
  • B. Use regedit to export the following key: HKLM\Software\Microsoft\Office\15.0\User Settings\ProjectRibbon. Ask the other project managers to import the key.
  • C. Save a Project File with the customizations to the ribbon in the file. Ask the other project managers to open the file.
  • D. Click on the Import/Export button to export the customizations to a file. Ask the other project managers to import the file.
Reveal Solution  Discussion  0

Correct Answer: D  🗳️

Question #2

You are a project manager who uses Project Professional 2013.
A senior stakeholder asks you to update your project to reflect your organization's scheduled two-week closure.
You need to reflect the closure within your schedule.
What should you do?

  • A. Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.
  • B. Open the Project Calendar and modify the default work week by setting the dates as non-working time.
  • C. Create a new calendar and assign this to the tasks that are scheduled over the period of closure.
  • D. Open the Project Calendar and enter the planned closure in the Exceptions tab.
Reveal Solution  Discussion  0

Correct Answer: D  🗳️

Question #3

You are a project manager who uses Project Professional 2013.
All resources in your project schedule have availability of 8 hours per day. You notice that several of the resources on the project are overallocated. You decide to level the project to help resolve the overallocations for the resources.
Team members often do not work at the same time when completing their work on the tasks.
You need to resolve the overallocations by using the Resource Leveling function.
What should you do?

  • A. Click the Level only within available slack option.
  • B. Click the Leveling can adjust individual assignments on a task option.
  • C. Click the Level resources with a proposed booking type option.
  • D. Click Clear Leveling.
Reveal Solution  Discussion  0

Correct Answer: B  🗳️

Question #4

DRAG DROP
You are a project manager who uses Microsoft Project 2013.
A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time.
You need to bring on another resource to assist with the remaining 50% of the work while ensuring that the same amount of work gets done in the two days that were originally committed.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)

Reveal Solution  Discussion  0

Correct Answer:


Explanation:
Box 1: Assign the additional resource to the task.
Box 2: Set the task type to fixed work,
Box 3: Change both the new and existing resource units to 50%.
Note:
For a fixed-work task

Question #5

You are using Project Standard 2013.
You want the ability to see only tasks that have finish dates past their deadline date You need to achieve this goal using a custom field.
What should you do?

  • A. Use the Task Text30 custom field, also known as the Deadline Flag, since it automatically provides this capability.
  • B. Create a Lookup containing the values Yes and No against the Task Text1 custom field.
    Write a formula that compares the deadline date to the finish date and displays the correct value from the Lookup table.
  • C. Use the Task Flagl5 custom field. Write a formula that compares the deadline date to the finish date, and set the result to Yes or No.
  • D. Rename the Task Number1 custom field to Deadline passed. Write a formula that compares the deadline date to the finish date and displays Yes or No in the field.
Reveal Solution  Discussion  0

Correct Answer: C  🗳️

What Clients Say About Us

I used this version and passed this 074-343 exam.

Donna Donna       4.5 star  

Passed to day in France with a nice score 90%, still valid. New questions is little. Thanks a lot. The premium exams are latest.

Meredith Meredith       4.5 star  

Thank you for the great 074-343 study guides.

Teresa Teresa       5 star  

This is a good 074-343 practice dump to preparing for the 074-343 exam. Would recommend it to you!

Evan Evan       5 star  

Few questions are different with the Questions from the dump but never mind. Dumps are valid. I passed my exam yesterday. Thank you. Good luck to you all.

Michell Michell       4.5 star  

Very helpful exam material for 074-343 here at VCEDumps. Bought the pdf file and practise exam software and it helped me understand the nature of the exam. Great work team VCEDumps.

Brook Brook       4.5 star  

I have failed the 074-343 exam once, but 074-343 exam dumps in VCEDumps helped me pass the exam this time, really appreciate!

Doreen Doreen       4 star  

I will try other Microsoft exams next month.

Kerr Kerr       4 star  

I did my entire preparation from VCEDumps 074-343 exam study guide and with it my scores were absolutely excelled. I found the VCEDumps study material very informative

James James       4.5 star  

After i passed my 074-343 exam, then i found i was spending time and effort effectively on the right 074-343 learning materials for the exam. It is worthy to buy!

Hogan Hogan       4 star  

I took the 074-343 exam last week and passed, I encountered many similar question in real exam. Thanks 074-343 exam dumps give me a chance to achieve my dream.

Joyce Joyce       4.5 star  

There is no need of practicing more questions! These 074-343 exam questions are enough for you to pass the exam. I have passed the exam with good marks. Thanks!

Tina Tina       4.5 star  

Just passed with this 074-343 exam questions! At least 95% of questions and answers were in the exam. Almost all of them are covered. Thank you!

Martha Martha       4 star  

Most of my colleagues scared me pointing to the difficult syllabus of exam Microsoft Project 074-343 . To an extent they were right but one new question

Kirk Kirk       4.5 star  

VCEDumps provides the latest exam dumps for the 074-343 exam. Helped me a lot in preparing so well. Passed my exam with very good scores. Thank you VCEDumps.

Yves Yves       4 star  

The 074-343 exam braindumps are 90% valid. It is glad to tell you that i got my certifications last week. Thanks!

Sarah Sarah       4.5 star  

Thanks for Microsoft Project sending me the update.

Jim Jim       4.5 star  

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

QUALITY AND VALUE

VCEDumps Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

EASY TO PASS

If you prepare for the exams using our VCEDumps testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

TESTED AND APPROVED

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

TRY BEFORE BUY

VCEDumps offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.