C_TS410_1909 Exam Dumps, C_TS410_1909 Practice Test Questions [Q31-Q52]

Share

C_TS410_1909 Exam Dumps, C_TS410_1909 Practice Test Questions

PDF (New 2023) Actual SAP C_TS410_1909 Exam Questions

NEW QUESTION 31
Which of the following functions can result in a creation of reservations for a production order? There are 2 correct answers to this question.

  • A. Calculate production cost
  • B. Convert planned order to production order
  • C. Record manufacturing activities
  • D. Release production order

Answer: B,D

 

NEW QUESTION 32
What MRP control parameter defines the scope of a planning run?

  • A. Lot size
  • B. Planning mode
  • C. Processing key
  • D. Procurement type

Answer: C

 

NEW QUESTION 33
When creating condition master records, what data properties does the condition type control? There are 2 correct answers to this question.

  • A. Currency
  • B. Scales
  • C. Sales organization
  • D. Validity period

Answer: B,D

 

NEW QUESTION 34
What can a planned order be converted to? There are TWO correct answers for this Question.

  • A. A production order
  • B. A purchase requisition
  • C. A purchase order
  • D. A planned independent requirement

Answer: A,B

 

NEW QUESTION 35
What is required to report on a combination of characteristics, such as customer, product, and region?

  • A. Primary cost elements
  • B. Profit centers
  • C. G/L accounts
  • D. Profitability segments

Answer: D

 

NEW QUESTION 36
Which objects can be assigned to a profit centers? There are 2 correct answers to this question.

  • A. Operating concern
  • B. Sales order item
  • C. Sales organization
  • D. Material

Answer: B,D

 

NEW QUESTION 37
What master data records are used in advanced planning? There are THREE correct answers for this Question

  • A. Location
  • B. Product
  • C. Bill of material
  • D. Work center
  • E. Resource

Answer: A,B,E

 

NEW QUESTION 38
A goods issue is posted against a production order. What are the results? There are THREE correct answers for this Question

  • A. Internal labor costs are posted
  • B. A controlling document is created
  • C. Actual costs are updated in the production order
  • D. A warehouse task is created
  • E. The material reservation is reduced

Answer: B,C,E

 

NEW QUESTION 39
Which of the following sequences of purchase-to-pay process steps is valid?

  • A. Determination of requirements .Vendor selection , Purchase order handling .Goods receipt .Invoice verification
  • B. Source of supply determination .Vendor selection , Determination of requirements Purchase order handling .Goods receipt
  • C. Determination of requirements .Purchase order handling . Handling of payments .Goods receipt .Invoice verification
  • D. Vendor selection .Source of supply determination , Purchase order monitoring .Goods receipt .Handling of payments

Answer: A

 

NEW QUESTION 40
Which maintenance order element includes the field values for work center, control key, and activity type?

  • A. Actual cost
  • B. Assembly
  • C. Order header
  • D. Operation

Answer: D

 

NEW QUESTION 41
Which of the following areas are part of SAP SuccessFactors Employee Central? There are THREE correct answers for this Question

  • A. Success and Development
  • B. Employee Data
  • C. Learning Management
  • D. Payroll
  • E. Organization management

Answer: B,D,E

 

NEW QUESTION 42
What type of document is generated for an external network activity?

  • A. Sales order
  • B. Planned order
  • C. Reservation
  • D. Purchase requisition

Answer: D

 

NEW QUESTION 43
What is the correct sequence of steps in the sales and distribution process? Please choose the correct answer.

  • A. 1. Create sales order
    2. Check availability
    3. Process delivery document
    4. Post goods issue
  • B. 1. Check availability
    2. Create sales order
    3. Post goods issue
    4. Billing
  • C. 1. Create sales order
    2. Check availability
    3. Plan transportation
    4. Post goods issue
  • D. 1. Check availability
    2. Create sales order
    3. Billing
    4. Post goods issue

Answer: A

 

NEW QUESTION 44
What needs to be entered to create a business partner? There are TWO correct answers for this Question.

  • A. Account group
  • B. Business partner role
  • C. Business partner type
  • D. Partner functions

Answer: A,B

 

NEW QUESTION 45
Which objects can you settle?
There are Three correct answers for this Question

  • A. Profitability segment
  • B. Maintenance order
  • C. Cost center
  • D. Work breakdown structure (WBS) element

Answer: B,D

 

NEW QUESTION 46
What does the material ledger in SAP S/4HANA enable? There are TWO correct answers for this Question

  • A. Material valuation in multiple currencies
  • B. Reporting of all materials required during maintenance processing
  • C. Recording of all business transactions
  • D. Reporting for parallel accounting

Answer: A,D

 

NEW QUESTION 47
What are the benefits of using a business partner in SAP S/4HANA? There are TWO correct answers for this Question

  • A. You can maintain multiple addresses for an entity
  • B. It provides a harmonized architecture
  • C. General data is unique to each role
  • D. Vendors are managed separately from customers

Answer: A,B

 

NEW QUESTION 48
What is an element that you can assign to the SAP Human Management organizational structure?

  • A. Cost center
  • B. Profitability segment
  • C. Operating concern
  • D. Cost element

Answer: A

 

NEW QUESTION 49
Which documents are created when you post a valuated goods receipt for consumable materials? There are TWO correct answers for this Question

  • A. Accounting document
  • B. Sales order document
  • C. Controlling document
  • D. Vendor invoice document

Answer: A,C

 

NEW QUESTION 50
In your warehouse, you want to ensure that material is putaway in the ideal bin to improve efficiency. What SAP Extended Warehouse Management feature do you implement?

  • A. Slotting/rearrangement
  • B. Wave management
  • C. Yard management
  • D. Cross-docking

Answer: A

 

NEW QUESTION 51
When would you use a statistical key figure?

  • A. To collect actual expenses for an area of responsibility
  • B. To distribute primary expenses in a standard cost element
  • C. To use as a tracing factor in an assessment
  • D. To identify internal cost flows

Answer: B

 

NEW QUESTION 52
......

Updated Jan-2023 Pass C_TS410_1909 Exam - Real Practice Test Questions: https://www.vcedumps.com/C_TS410_1909-examcollection.html

Dumps Moneyack Guarantee - C_TS410_1909 Dumps UpTo 90% Off: https://drive.google.com/open?id=1QiWJuw3urW25TgJiYaRdu6piyKEUMuPJ