Download C-S4PPM-2021 Exam Dumps Questions to get 100% Success in SAP
100% Accurate Answers! C-S4PPM-2021 Actual Real Exam Questions
SAP C-S4PPM-2021 is a certification exam that is designed to test the knowledge and skills of professionals in the field of SAP S/4HANA Portfolio and Project Management. Certified Application Associate - SAP S/4HANA Portfolio and Project Management certification exam is intended for individuals who have a good understanding of how to implement and customize SAP S/4HANA Portfolio and Project Management solutions. C-S4PPM-2021 exam is designed to validate the candidate's knowledge of the features and functions of SAP S/4HANA Portfolio and Project Management, and their ability to configure and use these solutions.
SAP S/4HANA Portfolio and Project Management module is used to manage portfolios, projects, and resources in an organization. It provides tools for project planning, execution, and monitoring. The module also includes functionalities for resource management, financial management, and analytics. A certified SAP consultant with expertise in this module can help organizations to streamline their project management processes, reduce costs, and improve project delivery.
NEW QUESTION # 49
You have defined an item template. When you create a new item, you notice that you cannot select the template.
What could be the reason for this?
NOTE: There are 2 correct answers to this question
- A. The item template is not available in the selected bucket
- B. The item template has the Activate status
- C. The item template has a different item type
- D. The item template start date is in the future
Answer: A,C
NEW QUESTION # 50
Which of the following are consequence of releasing a phase?
NOTE: There are 2 correct answers to this question
- A. The phase type is set to read-only
- B. Predecessor phases are assigned the status locked
- C. Lower-level tasks and checklist are release
- D. Additional tasks cannot be added to the phase
Answer: A,C
NEW QUESTION # 51
How are capacity planning values rolled up along the bucket hierarchy?
- A. Item values are rolled up to buckets via the review
- B. Item values are rolled up directly to buckets
- C. Item values are rolled up to buckets via the collection
- D. Project values are rolled up directly to buckets
Answer: B
NEW QUESTION # 52
Decision Flow management is delivered with standard scenarios.
For which combination of object types can you define a standard attitude synchronization?
- A. Portfolio item and WBS element
- B. Decision point and PS project definition
- C. Decision point and activity milestone
- D. Decision point and WBS element
Answer: D
NEW QUESTION # 53
What must you do before you can use multiple currencies in financial planning in portfolio management?
- A. Select multiple currencies in the portfolio definition
- B. Define a subnet of currencies in portfolio and project management
- C. Define a subnet of currencies in project system
- D. Select multiple currencies in the portfolio item
Answer: C
NEW QUESTION # 54
What is the priority field in the project definition of a project management project used for?
- A. To determine the scheduled dates for the project
- B. To determine the approval authorizations required
- C. To support the evaluation of projects
- D. To restrict the selection of project types
Answer: C
NEW QUESTION # 55
Which of the following can be viewed in the item dashboard?
NOTE: There are 3 correct answers to this question.
- A. Standard fields
- B. Custom fields
- C. metrics
- D. authorizations
- E. Documents
Answer: A,B,C
NEW QUESTION # 56
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?
- A. The flexible Assignment indicator is active in role type customizing
- B. The role has the staffing in preparation status
- C. The role has the staffing in process status
- D. The Distribution indicator is active role type customizing
Answer: B
NEW QUESTION # 57
You have created a portfolio with the bucket levels and wants to create a portfolio item.
When can you create the portfolio item?
- A. At the lowest bucket level
- B. At multiple bucket levels
- C. At any bucket level
- D. At the highest bucket level
Answer: A
NEW QUESTION # 58
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.
- A. Your role and business partner are assigned to task that have the created status
- B. Your role and business partner are assigned to tasks that have the in process status
- C. Your user is not assigned to a business partner
- D. Your personal number is not assigned to a business partner
Answer: A,D
NEW QUESTION # 59
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?
- A. Qualification determination
- B. Staffing by authorization
- C. Role assignment and staffing
- D. Extended staffing
Answer: D
NEW QUESTION # 60
You review the capacity planning values at bucket level in portfolio management.
Which function can you use to view the items that are assigned to a bucket directly in capacity planning?
Include subobjects
- A. BCV Reporting
- B. Distribution
- C. View Chart
Answer: A
NEW QUESTION # 61
How do you make a decision point field a required field for a specific portfolio item?
- A. Make the filed a required field for the decision point and assign the item type to the portfolio In customizing
- B. Make the filed a required field for the combination of the item and decision point in customizing for the portfolio type
- C. Make the field a require field for the combination of decision point and portfolio type in customizing for the item type
- D. Make the filed a required field for the combination point and assign the item and decision point in customizing for the portfolio type
Answer: B
NEW QUESTION # 62
When you create an item from an initiative, which of the following objects are authorizations inherited from?
NOTE: There are 3 correct answers to this question
- A. Portfolio
- B. Project system project
- C. Parent bucket
- D. Project management project
- E. initiative
Answer: A,C,E
NEW QUESTION # 63
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?
- A. Portfolio dashboard
- B. Evaluation
- C. BI report
- D. Business Context Viewer (BCV)
Answer: D
NEW QUESTION # 64
......