Updated Jan 27, 2022 Test Engine to Practice Test for C-TS413-2020 Valid and Updated Dumps [Q45-Q62]

Share

Updated Jan 27, 2022 Test Engine to Practice Test for C-TS413-2020 Valid and Updated Dumps

Exam Questions for C-TS413-2020 Updated Versions With Test Engine


SAP C-TS413-2020 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Asset Management" certification exam verifies that the candidate has the fundamental and core knowledge in the area of Asset Management required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.


C-TS413-2020 Exam Certification Details:

Exam:80 questions
Duration:180 mins
Sample Questions: SAP C-TS413-2020 Exam Sample Question
Cut Score:64%


SAP C-TS413-2020 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
User Interface and User Experience < 8%

Descibe UI technologies and client types used with SAP S/4HANA Asset Management.

Project-oriented Maintenance < 8%

Describe and implement various scenarios for project-oriented maintenance.

Refurbishment of Spare Parts < 8%

Describe and implement the process of internal and external refurbishment of spare parts.

Preventive Maintenance > 12%

Describe the options for preventive maintenance using task lists, single-cycle, time-based strategy and performance-based strategy maintenance plans.

Breakdown Maintenance < 8%

Describe and implement the process of breakdown maintenance using traditional and FIORI-based applications.

Corrective Maintenance > 12%

Describe and implement the process of corrective maintenance using traditional and FIORI-based applications.

Technical Objects > 12%

Describe and implement technical asset structures following fundamental concepts and building the integration to key neighbour applications.

Organizational Units and Master Data 8% - 12%

Describe and implement the necessary organizational units especially regarding the integration into the general logistics and accounting units.

Mobile Maintenance < 8%

Describe the available mobile applications for SAP S/4HANA Asset Management


 

NEW QUESTION 45
You have created a new equipment category, "linear", with the corresponding view profile. Which fields appear in the equipment linear data tab? Note: There are 3 correct Answers to this question.

  • A. Unit of measure
  • B. Segment
  • C. Start marker
  • D. Type of offset
  • E. Object network

Answer: A,C,D

 

NEW QUESTION 46
You want to view transactional and analytical processing data in the Technical Object Breakdowns app.
What is the source of the information?

  • A. SAP Query InfoSet
  • B. PMIS InfoSet
  • C. BW InfoCube
  • D. Core Data Service View

Answer: D

 

NEW QUESTION 47
You want to have several plan dates calculated in a maintenance plan. Which scheduling parameter do you use?

  • A. Offset
  • B. Scheduling indicator
  • C. Scheduling period
  • D. Call horizon

Answer: C

 

NEW QUESTION 48
You need to create a new functional location. Which actions can you perform with the SAP Fiori app
"Create Technical Object"? Note: There are 3 correct Answers to this question.

  • A. Create a task list for functional location.
  • B. Edit classification data and characteristics.
  • C. Assign documents.
  • D. Change a reference location.
  • E. Assign a subordinate piece of equipment.

Answer: B,C,D

 

NEW QUESTION 49
Which operations can the responsible person perform after a maintenance order is technically completed? Note: There are 3 correct Answers to this question.

  • A. Change the settlement rule.
  • B. Create an invoice receipt for delivered materials.
  • C. Lock or unlock the order.
  • D. Change the planned costs.
  • E. Update the estimated costs.

Answer: A,B,C

 

NEW QUESTION 50
You want to assign a maintenance planning plant directly to an organizational unit. Which of the following units can you use?

  • A. Location
  • B. Maintenance work center
  • C. Maintenance planner groups
  • D. Controlling area

Answer: C

 

NEW QUESTION 51
Which parameter in a maintenance strategy do you use to set the start/end date of the maintenance order?

  • A. Initial/subsequent buffer
  • B. Scheduling type
  • C. Package offset
  • D. Call horizon

Answer: A

 

NEW QUESTION 52
Which statement is correct when planning maintenance work that is to be carried out by an external company?

  • A. In the control key assigned to the order operation, the "Service" indicator must always be activated.
  • B. A service master record must always be assigned to the external order operation.
  • C. If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system.
  • D. If you assign a control key with indicator "Service" for an external service, you have to enter the actual values via the service entry sheet.

Answer: D

 

NEW QUESTION 53
Which parameter in the material master is a prerequisite for refurbishment?

  • A. Valuation category C (condition-based)
  • B. Valuation category B (in-house/external procurement)
  • C. Valuation class 8000
  • D. Valuation type H (origin)

Answer: A

 

NEW QUESTION 54
How do you set up the visible tiles for a specific user in SAP Fiori launchpad? Note: There are 2 correct Answers to this question.

  • A. By assigning a PFCG role with an SAP Fiori catalog
  • B. By assigning a PFCG role with an SAP Fiori tile group
  • C. By assigning a portal role with an SAP Fiori catalog
  • D. By assigning the tiles directly

Answer: A,B

 

NEW QUESTION 55
Which functions are available in the Resource Scheduling for Maintenance Planners app? Note: There are 2 correct Answers to this question.

  • A. Schedule and dispatch maintenance operations by shifts.
  • B. Monitor maintenance order operations due in the next 4 weeks.
  • C. Cancel dispatched maintenance order operations.
  • D. Print job papers from a maintenance order.

Answer: B,C

 

NEW QUESTION 56
What are the prerequisites for serializing a piece of equipment? Note: There are 3 correct Answers to this question.

  • A. Assign a serial number profile to the equipment category.
  • B. Maintain a serial number for an existing equipment master.
  • C. Add a serialized material to the construction type field of the equipment master.
  • D. Assign a serial number profile to the related material master.
  • E. Add a serialized material to the equipment serial data view.

Answer: C,D,E

 

NEW QUESTION 57
Which SAP UI technology is used for the Report and Repair Malfunction app?

  • A. Web Dynpro
  • B. SAP GUI for Windows
  • C. SAPUI5
  • D. SAP GUI for HTML

Answer: A

 

NEW QUESTION 58
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct Answers to this question.

  • A. Start date
  • B. Factory calendar
  • C. Scheduling indicator
  • D. Scheduling period

Answer: A,D

 

NEW QUESTION 59
You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months. Which parameter do you have to use to map this in the system?

  • A. Shift factor
  • B. Maintenance package offset
  • C. Maintenance plan category
  • D. Scheduling indicator

Answer: B

 

NEW QUESTION 60
Which statements related to the creation of maintenance orders are correct? Note: There are 2 correct Answers to this question.

  • A. When an order is created based on a single notification, this notification becomes the header notification.
  • B. The document within the document management system can be assigned only at operational level.
  • C. The assignment of the header notification to an order CANNOT be deleted.
  • D. The long text of the reference notification can be automatically copied as the long text of the order.

Answer: A,D

 

NEW QUESTION 61
What is a valid partner type within the partner determination procedure?

  • A. Business partner (gen.)
  • B. Vendor (external)
  • C. Planner group
  • D. Purchasing organization

Answer: A

 

NEW QUESTION 62
......