With 712-50 exam, the EC-Council CCISO (Certified Chief Information Security Officer) certification is associated. This one is the gold-standard of IT executive management certifications and is famed to infuse core knowledge related to IS control, human capital management, program development, financial expertise, and the like. Because of this high-end learning, the CCISO designation is the key to get placed in pivotal information security management job roles. Using the professionally designed exam domains, such a certification fills the gap that exists between real-time work expertise that a CISO aspirant needs at the job and what an emerging CISO already has.
NEW QUESTION 14
The FIRST step in establishing a security governance program is to?
- A. Conduct a risk assessment.
- B. Obtain senior level sponsorship
- C. Prepare a security budget.
- D. Conduct a workshop for all end users.
Answer: B
NEW QUESTION 15
According to ISO 27001, of the steps for establishing an Information Security Governance program listed below, which comes first?
- A. Define Information Security Policy
- B. Identify threats, risks, impacts and vulnerabilities
- C. Decide how to manage risk
- D. Define the budget of the Information Security Management System
Answer: A
NEW QUESTION 16
Access Control lists (ACLs), Firewalls, and Intrusion Prevention Systems are examples of
- A. User segmentation controls
- B. Network based security preventative controls
- C. Network based security detective controls
- D. Software segmentation controls
Answer: B
NEW QUESTION 17
Which of the following can the company implement in order to avoid this type of security issue in the future?
- A. Network based intrusion detection systems
- B. An audit management process
- C. A security training program for developers
- D. A risk management process
Answer: C
NEW QUESTION 18
Which of the following is a term related to risk management that represents the estimated frequency at which a threat is expected to transpire?
- A. Annualized Rate of Occurrence (ARO)
- B. Single Loss Expectancy (SLE)
- C. Exposure Factor (EF)
- D. Temporal Probability (TP)
Answer: A
NEW QUESTION 19
You work as a project manager for TYU project. You are planning for risk mitigation. You need to quickly identify high-level risks that will need a more in-depth analysis.
Which of the following activities will help you in this?
- A. Quantitative analysis
- B. Risk mitigation
- C. Estimate activity duration
- D. Qualitative analysis
Answer: D
Explanation:
Explanation/Reference:
NEW QUESTION 20
SCENARIO: Critical servers show signs of erratic behavior within your organization's intranet. Initial information indicates the systems are under attack from an outside entity. As the Chief Information Security Officer (CISO), you decide to deploy the Incident Response Team (IRT) to determine the details of this incident and take action according to the information available to the team.
During initial investigation, the team suspects criminal activity but cannot initially prove or disprove illegal actions. What is the MOST critical aspect of the team's activities?
- A. Regular communication of incident status to executives
- B. Eradication of malware and system restoration
- C. Preservation of information
- D. Determination of the attack source
Answer: C
NEW QUESTION 21
Where does bottom-up financial planning primarily gain information for creating budgets?
- A. By reviewing last year's program-level costs and adding a percentage of expected additional portfolio costs
- B. By adding the cost of all known individual tasks and projects that are planned for the next budgetary cycle
- C. By adding all capital and operational costs from the prior budgetary cycle, and determining potential financial shortages
- D. By adding all planned operational expenses per quarter then summarizing them in a budget request
Answer: D
NEW QUESTION 22
Scenario: The new CISO was informed of all the Information Security projects that the section has in progress. Two projects are over a year behind schedule and way over budget.
Which of the following will be most helpful for getting an Information Security project that is behind schedule back on schedule?
- A. More training of staff members
- B. Upper management support
- C. More frequent project milestone meetings
- D. Involve internal audit
Answer: B
NEW QUESTION 23
Which of the following statements about Encapsulating Security Payload (ESP) is true?
- A. It uses TCP port 22 as the default port and operates at the application layer.
- B. It uses UDP port 22
- C. It is a text-based communication protocol.
- D. It is an IPSec protocol.
Answer: D
NEW QUESTION 24
In MOST organizations which group periodically reviews network intrusion detection system logs for all systems as part of their daily tasks?
- A. Database Administration
- B. Compliance
- C. Internal Audit
- D. Information Security
Answer: D
NEW QUESTION 25
When operating under severe budget constraints a CISO will have to be creative to maintain a strong security organization.
Which example below is the MOST creative way to maintain a strong security posture during these difficult times?
- A. Download open source security tools and deploy them on your production network
- B. Download security tools from a trusted source and deploy to production network
- C. Download trial versions of commercially available security tools and deploy on your production network
- D. Download open source security tools from a trusted site, test, and then deploy on production network
Answer: D
NEW QUESTION 26
At which point should the identity access management team be notified of the termination of an employee?
- A. During the monthly review cycle
- B. Immediately so the employee account(s) can be disabled
- C. At the end of the day once the employee is off site
- D. Before an audit
Answer: B
NEW QUESTION 27
The process of identifying and classifying assets is typically included in the________________.
- A. Threat analysis process
- B. Business Impact Analysis
- C. Asset configuration management process
- D. Disaster Recovery plan
Answer: B
NEW QUESTION 28
The PRIMARY objective for information security program development should be:
- A. Establishing strategic alignment with business continuity requirements.
- B. Establishing incident response programs.
- C. Identifying and implementing the best security solutions.
- D. Reducing the impact of the risk to the business.
Answer: D
NEW QUESTION 29
Acme Inc. has engaged a third party vendor to provide 99.999% up-time for their online web presence and had them contractually agree to this service level agreement. What type of risk tolerance is Acme exhibiting? (choose the BEST answer):
- A. low risk-tolerance
- B. moderate risk-tolerance
- C. high risk-tolerance
- D. medium-high risk-tolerance
Answer: A
NEW QUESTION 30
Which of the following is the MAIN reason to follow a formal risk management process in an organization that hosts and uses privately identifiable information (PII) as part of their business models and processes?
- A. Fiduciary responsibility to safeguard credit card information
- B. Need to transfer the risk associated with hosting PII data
- C. Need to comply with breach disclosure laws
- D. Need to better understand the risk associated with using PII data
Answer: D
NEW QUESTION 31
You currently cannot provide for 24/7 coverage of your security monitoring and incident response duties and your company is resistant to the idea of adding more full-time employees to the payroll. Which combination of solutions would help to provide the coverage needed without the addition of more dedicated staff? (choose the best answer):
- A. Employ an assumption of breach protocol and defend only essential information resources
- B. Deploy a SEIM solution and have current staff review incidents first thing in the morning
- C. Contract with a managed security provider and have current staff on recall for incident response
- D. Configure your syslog to send SMS messages to current staff when target events are triggered
Answer: C
NEW QUESTION 32
You are the CISO of a commercial social media organization. The leadership wants to rapidly create new methods of sharing customer data through creative linkages with mobile devices. You have voiced concern about privacy regulations but the velocity of the business is given priority. Which of the following BEST describes this organization?
- A. Risk conditional
- B. Risk tolerant
- C. Risk averse
- D. Risk minimal
Answer: B
NEW QUESTION 33
......
New 712-50 Exam Dumps with High Passing Rate: https://www.vcedumps.com/712-50-examcollection.html